Integrated Solutions and Services
Integrated Solutions and Services
Working with a National Wood and Forest Products Company
Electrical | Instrumentation & Controls | FabricationProject Scope:
Electrical
Installing 3 new switchgears and disconnects for every motor, 3 electrical panels and 2 transformers and all wiring and components
Installing 7,000’ of cable tray (all tray had to be installed vertically so no wood accumulation would happen)
Installing 170 lights and 60 receptacles, plus all wiring
Pulling 87,000’ of cable and performing 7,500 terminations
Instrumentation & Controls
Installing 242 instruments, cable and wiring
Installing 10 PLC panels
Working on additions to 3 existing PLC panels
Installing Rupture vent control boxes
Fabrication
Cable tray supports
Disconnect stands